Nigerian Govt 🔊Announces Fresh Repair of 🌉Third Mainland Bridge

The Federal Controller of Works in Lagos, Mr Adedamola Kuti, has said that traffic arrangements were ongoing to begin another phase of major repair on the Third Mainland Bridge.

Kuti told the News Agency of Nigeria (NAN) in Lagos that results of investigative tests on the bridge were ready and that contractors would move to site at the completion of the traffic management architecture.

“We are also going to repair some of the piles or pillars carrying the bridge; that is the next phase that we are doing; so work will soon begin on Third Mainland Bridge,’’ he said.

“Work is ongoing on the Dorman Long Bridge, you can drive smoothly on it now and all the guard rails and expansion joints are being replaced.

According to him, although procurement issues affected project delivery, there are enough materials from Alaka Bridge expansion joint works to repair adjoining bridges on the Apapa-Ijora axis.

If you are coming in from Surulere and going to Alaka, the intersection is between Iganmu and Eko Bridge, I gave instruction to fix it.

“Also, at the intersection outwards Apapa and inwards Apapa from Costain area, there is a very bad expansion joint, I just gave instruction to fix it,” Kuti said.

Published by DEAN 360

Isah Abdullahi (born on September 12th 1996) is a Nigerian blogger, writer, entrepreneur, social media expert, and a political analyst.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

Create your website with WordPress.com
Get started
%d bloggers like this: